Working beyond its permissible capacity, Svinninge municipal wastewater treatment plant (Denmark) needed to increase the existing plant’s capacity to ensure effective treatment.
To meet our client’s needs, Cella™ was chosen, this decision having been driven by the technology’s sustainability and small ecological footprint as well as the compactness and efficiency of its process.
The plant began operations in the second quarter of 2024. After tuning the equipment as well as the control system, the biological process was started up at the beginning of the third quarter of 2024. The process is approaching the target effluent concentrations (TIN < 4 mg-N/l) while treating 50–70% of the load to the whole treatment plant. Target performance is expected to be achieved at the end of the third quarter of 2024